Roll Up function
Material Resource rolled up?
% Work Complete
Percentage
Calculated: Act. Work/Total Work
NA
Accrue At
Enumerated
No
NA
Actual Cost
Currency
Sum
Yes
Actual Finish
Date
Max (if there is an NA, then value = NA)
Yes
Actual Overtime Cost
Currency
Sum
Yes
Actual Overtime Work
Duration
Sum
No
Actual Start
Date
Min (if there is an NA, then value = NA)
Yes
Actual Work
Duration
Sum
No
ACWP
Currency
Sum
Yes
Assignment
Boolean
No
NA
Available From
Date
Min
Yes
Available To
Date
Max
Yes
Base Calendar
Text
No
Yes
Baseline Cost
Currency
Sum
Yes
Baseline Work
Duration
Sum
No
BCWP
Currency
Sum
Yes
BCWS
Currency
Sum
Yes
Can Level
Boolean
No
NA
Code
Text
No
NA
Confirmed
Boolean
No
NA
Cost
Currency
Sum
Yes
Cost Per Use
Currency
Sum
Yes
Cost Variance
Currency
Calculated
NA
Cost1 - Cost10
Currency
Custom Field formula
Yes
Date1 - Date10
Date
Custom Field formula
Yes
Duration1 – Duration10
Duration
Custom Field formula
Yes
Email Address
Text
No
NA
Finish
Date
Max
Yes
Finish1 – Finish10
Date
Custom Field formula
Yes
Flag1 - Flag20
Boolean
Custom Field formula
Yes
Group
Text
No
NA
Hyperlink
Text
No
NA
Hyperlink Address
Text
No
NA
Hyperlink Href
Text
No
NA
Hyperlink SubAddress
Text
No
NA
ID
Integer
No
NA
Indicators
Indicator
No
NA
Initials
Text
No
NA
Linked Fields
Boolean
No
NA
Max Units
Percentage/Number
Sum
No
Name
Text
No
NA
Notes
Text
No
NA
Number1 - Number20
Number
Custom Field formula
Yes
Objects
Boolean
No
NA
Overallocated
Boolean
No
NA
Overtime Cost
Currency
Sum
Yes
Overtime Rate
Currency Rate