The value for specific rolled up task fields in a group summary header is summarized in the following table:
Task Field
Type
Rollup Function
% Complete
Percentage
(Actual Duration / Duration) * 100
% Work Complete
Percentage
(Actual Work / Work) * 100
Actual Cost
Currency
Sum
Actual Duration
Duration
Actual Finish - Actual Start based on project calendar and tools.option setting
Actual Finish
Date
Max(if there is an NA, then value = NA)
Actual Overtime Cost
Currency
Sum
Actual Overtime Work
Duration
Sum
Actual Start
Date
Min(if there is an NA, then value = NA)
Actual Work
Duration
Sum
ACWP
Currency
Sum
Assignment
Boolean
No
Assignment Delay
Duration
No
Assignment Units
Percentage/Number
No
Baseline Cost
Currency
Sum
Baseline Duration
Duration
Baseline Finish - Baseline Start based on project calendar and tools.option setting
Baseline Finish
Date
Max
Baseline Start
Date
Min
Baseline Work
Duration
Sum
BCWP
Currency
Sum
BCWS
Currency
Sum
Confirmed
Boolean
OR
Constraint Date
Date
No
Constraint Type
Enumerated
No
Contact
Text
No
Cost
Currency
Sum
Cost Rate Table
Enumerated
No
Cost Variance
Currency
Sum
Cost1-10
Currency
Custom Field formula
Created
Date
MIN
Critical
Boolean
OR
CV
Currency
Sum
Date1-10
Date
Custom Field formula
Duration
Duration
Shed. Finish - Sched. Start based on project calendar and tools.option setting
Duration Variance
Duration
Baseline Dur. - Sceh Dur.
Duration1-10
Duration
Custom Field formula
Early Finish
Date
Max
Early Start
Date
Min
Effort Driven
Boolean
No
Estimated
Boolean
OR
External Task
Boolean
No
Finish
Date
Max
Finish Variance
Duration
Baseline Fin. - Sched. Fin.
Finish1-10
Date
Custom field formula
Fixed Cost
Currency
Sum
Fixed Cost Accrual
Enumerated
No
Flag1-20
Boolean
Custom field formula
Free Slack
Duration
No
Hide Bar
Boolean
No
Hyperlink
Text
No
Hyperlink Address
Text
No
Hyperlink Href